1.SEA of National power development master plan for the period 2011-2020 with outlook to 2030 (PDP VII)
2. EIA of hydropower plants in the Center and Highland region, propose solutions for envirenmental management and protection
3. Investment report of Quang Tri TPP
4. Verify EIA of the investment project and technical design of Vinh Tan 4 TPP
5. Verify EIA of the investment project of Formosa Dong Nai TPP
6. Verify EIA of the investment project of Long Son TPP
7. Verify EIA of the investment project and technical design of Song Hau 2 TPP
8. Site planning and investment project of Kim Son Ninh Binh TPP
9. Research on BOCM methedology for high effective coal-fired power plant in Vietnam
10. Solutions to control GHG in the coal-fired field and propose roadmap to apply these solutions
11. EIA for Ninh Thuan 2 NPP
12. EIA for habour item of Ninh Thuan 1 NPP
13. EIA for slag dump of Vung Ang 1 TPP
14. Technical design of slag dump of Vung Ang 1 TPP
15. Survey, EIA and site planning for investment report of NPP in Vietnam
16. Site planning and investment report of Cam Pha 3 TPP
17. Independent observation of environmental management plan, rehabitant plan and minority plan under the framework of Renewable Energy Development Project (REDP)
18.EIA for Van Phong 1 TPP
19. SEA for LNG site planning in the whole country up to 2020 with outlook to 2030
20. SEA for verifying the National power development plan for the period 2011-2020 with outlook to 2030 (PDP VII)
21. EIA for Western Hanoi 200kV and 500kV substations
22. EIA for Thuong Tin – Western Hanoi 500kV line